The Brief

Refurbishment of 5 bedroom duplex flat including forming 3 new en-suite shower rooms and relocating the kitchen.

The Challenge

Completion of the project to a high standard of finish by the original completion date whilst incorporating client variations equating to over 30% of the original contract value whilst allowing for restricted hours when noisy works could be carried out to ensure that the client was able to move back into the property by the required date with minimal disruption to the other residents.

The Result

Works were completed by the agreed date to the standards expected from this client resulting in repeat business for the client at their other properties.